| Phase | Scope | Modern Estate | French Château |
|---|---|---|---|
| 0 · Design & approvals Designer/architect drawings, Village of Rockville Centre building permit, architectural review for facade/roof work (Château). | Drawings, permits, orders placed | 6–10 weeks | 12–20 weeks |
| 1 · Exterior envelope Château path is the long pole: stone cladding ~8–12 weeks on site after 10–16 week material lead; slate + mansard framing overlaps. | Facade finish, windows, roof (S2), doors | 4–8 weeks | 16–26 weeks |
| 2 · Interiors Paint/limewash, floors refinished, millwork & library, baths re-fitted, lighting swapped. House is livable-adjacent through most of it; floor refinish needs 1–2 weeks out. | All interior line items | 8–12 weeks | 12–18 weeks |
| 3 · Landscape & pool yard Hedging, beds/parterre, drive or motor court, pool deck, glass fence, fountain (S2). Weather-window dependent; overlaps Phase 2. | All site work | 4–8 weeks | 8–14 weeks |
| Realistic calendar, overlapped | 4–6 months | 10–14 months | |